Phase VIII – Project Warranty Period

Policies & Procedures for New Construction, Renovations and Maintenance Projects

Latent (hidden) defects in the Work of the contract discovered within 12 months after the Architects’ issuance date on the Certificate of Substantial Completion and Punch List are considered warranty defects that the Contractor is required to correct at no additional cost to the Parish. Upon discovery of such defects in the Work, the Parish shall notify the Contractor of the problem in writing with copies to the design consultant and DFM.